Evaluasi Metode Lean Project Management Pada Proyek Pelaksanaan Pembangunan Tangki Premium, ADO, dan RFO di Pertamina RU V Balikpapan


Apriana Intan Permatasari(1), Anggriani Profita(2), Suwardi Gunawan(3),


(1) Universitas Mulawarman Samarinda
(2) Universitas Mulawarman Samarinda
(3) Universitas Mulawarman Samarinda

Abstract


The implementation of construction projects cannot be separated from various obstacles and failures. These obstacles and failures cannot be seen in real terms, but if they continue, their impact will be visible at the end of the project. So that everything in a project that does not add value or can be called a waste of waste. To overcome this, you can use the Lean Project Management method. Based on identification and interviews with the Premium, ADO, and RFO tank construction project parties at Pertamina RU V Balikpapan, wastes that have the potential to arise during project implementation are waiting, defects, and unpropriate processing of the eight existing wastes. Waiting and defects in this project are caused by environmental factors, humans, machines, materials and unappropriate processing caused by human factors. For the evaluation matrix for late arrivals, a value of 42 is obtained, for bad weather a value of 45 is obtained, the value of equipment damage is 39. The possible risk factors that arise during project implementation are determined based on identification and interviews with the project party, namely bad weather conditions, late arrival of materials, K3 (Occupational Health and Safety), equipment damage, rework.

 

 

Keywords:       Fishbone, FMEA, Lean Project Management, Waste

Keywords


Fishbone, FMEA, Lean Project Management, Waste

Full Text:

PDF

References


Artika, Dian., 2014, Penerapan Metode Lean Project Management dalam proyek konstruksi pada Pembangunan Gedung DPRD Kabupaten Ogan Ilir, Jurnal Teknik Sipil dan Lingkungan, Vol. 2 No. 1.

Ervianto, Wulfram I., 2004, Teori Aplikasi Manajemen Proyek Konstruksi. ANDI, Yogyakarta.

Frederika, Ariany., 2010, Analisis Percepatan Pelaksanaan dengan Menambah Jam Kerja Optimum pada Proyek Konstruksi (Studi Kasus: Proyek Pembangunan Super Villa, Peti Tenget-Badung). Jurnal Ilmiah Teknik Sipil, Vol. 14, No. 2.

Gasperz, Vincent., 2007, Total Quality Manajemen, PT. Graha Ilmu, Yogyakarta.

Gray, Clive., 2007, Pengantar Evaluasi Proyek, PT. Gramedia Pustaka Utama, Jakarta.

Goldartt, E.M., 1997. Critical Chain Massachusetts : North River Press.

Hanif, Yulianda Richma., Nendang Setyo Rukmi., & Susy Susanti., 2015, Perbaikan Kualitas Produk Keraton Luxury di PT. X dengan Menggunakan Metode Failure Mode And Effect Analysis (FMEA) dan Fault Tree Analysis (FTA). Jurnal Teknik Industri Itenas, Vol. 03, No.03.

Hapsari, Indri., 2011., Penerapan Metode Lean Project Management Dalam Perencanaan Proyek Kontruksi Pada Pembangunan Gedung SD N Bektiharjo II Semanding Tuban (Studi Kasus : CV. Chandra Setya Karya), Tugas Akhir. Jurusan Teknik Industri ITS, Surabaya.

Husen, Abrar., 2009, Manajemen Proyek. Andi Offset, Yogyakarta.

Karyono, Agus., 2014, Pendekatan Lean Manufacturing Untuk Menurunkan Waste Waiting Time dan Transportasi (Studi Kasus: CV. Riau Pallet). Tugas Akhir Universitas Negeri Sultan Syarif Kasim Riau.

Leach, Larry., 2005, Lean Project Management :Eight Principles for Success. Advanced Projects, 5239 South Pegasus Way Boise, Idaho 83716.

Narsha, & S, Nagabhusahan., 2013, Enhancing Project Management Efficiency Using Lean Concepts. IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 8, Issue 4.

Noer, Bustanul Arifin., & Dominggo Bayu Bagaskara., 2012, Perencanaan dan Pengendalian Proyek Periklanan Menggunakan Lean Critical Chain Project Management dan S-Curve Mentoring. Jurnal Tekni Pomits, Vol. 1, No. 1.

Project manajemen Institute, 2000, A guide to the Project management Body of Knowledge (PMBOK Guide). Pensylvania.

Sahid, Dadang Syarif Sihabudin., 2010, Implementasi Critical Path Method dan PERT Analysis pada Proyek Global Technology for Local Community. Jurnal Teknologi Informasi dan Telematika, Vol. 5.

Santoso, Budi., 2008, Manajemen Proyek. Graha Ilmu, Surabaya.

Sari, Erni., 2016. Analisis Resiko Proyek pada Pekerjaan Jembatan Sidamukti-Kadu di Majalengka dengan Metode FMEA dan Decision Tree. Jurnal J-Ensitec, Vol 03, No. 01.




DOI: https://doi.org/10.31289/jime.v6i1.6068

Article Metrics

Abstract view : 0 times
PDF - 0 times

Refbacks

  • There are currently no refbacks.


Program Studi Teknik Indusri, Fakultas Teknik, Universitas Medan Area
Universitas Medan Area, Jalan Kolam No. 1, Pasar V, Medan Estate, Sumatera Utara http://ojs.uma.ac.id/index.php/jimedan Email: jime@uma.ac.id
Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 International License