Analisis Keterlambatan Proyek Konstruksi di PT. PLN (Persero) UIP Sumbagut


Irwan Irwan(1), Melloukey Ardan(2), Nuril Mahda Rangkuti(3), Febrina Monalisa(4),


(1) Universitas Medan Area
(2) Universitas Medan Area
(3) Universitas Medan Area
(4) Universitas Medan Area

Abstract


Project delays are the main contribution to project cost overruns. The research intends to determine the main factor that cause delays in construction projects at PT. PLN (PERSERO) UIP Sumbagut. In this research, there were 31 variables which were grouped into 6 categories. The research is done by distributing questionnaires to 20 respondents from the owner who also handles the project. The data analysis used a comparison of the percentage, rank mean and standard deviation which were analyzed with Statistical Product and Service Solutions (SPSS). Based on the results of data analysis, it was found that the main factor causing delays in construction projects at PT. PLN (PERSERO) UIP Sumbagut is a shortage of manpower to complete a project. In addition, there are several other dominant factors, namely labor qualifications that do not meet standards; difficulties in financial cash flow and project funding from contractors; scheduling conflicts with sub-contractors and suppliers in the completion of work; security disturbances during the project.

Keywords


delay, contractor, questionnaire, mean, PLN, percentage, SPSS

Full Text:

PDF

References


Azhari, Aulia T. B.; Majid, I. A. (2014). Faktor-faktor Risiko yang Mempengaruhi Kinerja Kontraktor pada Pelaksanaan Proyek Infrastruktur di Kabupaten Aceh Jaya. Jurnal Teknik Sipil. Pascasarjana Universitas Syiah Kuala, Banda Aceh.

Aziz, A. M.; Marthen, R. W.; Dianita, R. K.; Hartono, N. (2016). Analisa Faktor Penyebab Keterlambatan Progress Terkait dengan Manajemen Waktu (Studi Kasus: Pelaksanaan Pembangunan Gedung UPT PP Politeknik Negeri Semarang). Wahana Teknik Sipil.

Bakhtiyar, Ariful, dkk. (2012). Analisis Faktor-faktor yang Mempengaruhi Keterlambatan Proyek Konstruksi Pembangunan Gedung di Kota Lamongan. Malang.

Dipohusodo I. (1995). Manajemen Proyek dan Konstruksi. Gramedia. Jakarta.

Irsyad, Muhammad Nur. (2015). Analisis Faktor-Faktor Yang Mempengaruhi Keterlambatan Proyek Konstruksi (Studi Kasus : Proyek Pembangunan Jembatan Rel Kereta Api Kuala Tanjung - Sumatera Utara). Skripsi Universitas Sumatera Utara. Medan

Nicholas. M, John. Project Management for Business, Engineering, and Technology

Pinori, Mickson. (2015). Analisis Faktor Keterlambatan Penyelesaian Proyek Konstruksi Gedung Terhadap Mutu, Biaya dan Waktu di Dinas Pekerjaan Umum Kota Manado. Manado

Sarwono, Jonathan. (2006). Metode Penelitian Kuantitatif dan Kualitatif. Graha Ilmu. Yogyakarta.

Sugiyono,P.D.(2010). Metode Penelitian Pendidikan, Pendekatan Kualitatif dan Kuantitatif. Alfa Beta. Bandung.

Santoso, Singgih. (2015). SPSS 20 Pengolahan Data Statistik di Era Informasi. PT. Elex Media Komputindo. Jakarta.

Widodo, Theodorus. (2013). Kajian Penyebab Keterlambatan Pelaksanaan Proyek Konstruksi Gedung di Kota Kupang. Jurnal Teknik Sipil. Vol 2, No. 2.

Wijayanthi, S. (2008). Faktor – Faktor Penyebab Keterlambatan Waktu Pembangunan Proyek Gedung Negara di Lingkungan Pemerintah Kota Kediri. Institut Teknologi Sepuluh November. Surabaya.




DOI: https://doi.org/10.31289/jcebt.v6i1.6817

Article Metrics

Abstract view : 0 times
PDF - 0 times

Refbacks

  • There are currently no refbacks.


Program Studi Teknik Sipil, Fakultas Teknik, Universitas Medan Area
Universitas Medan Area, Jalan Kolam No. 1, Pasar V, Medan Estate, Sumatera Utara http://ojs.uma.ac.id/index.php/jcebt dan Email: jcebt@uma.ac.id
Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 International License