PT. TCI is a company operating in the construction sector which handles the construction of several projects, one of which is the Tabernacle Church project. In carrying out the project work, several factors/problems arose, resulting in an extension of the project foundation construction stage and increasing the project period and costs. The use of the CPM and PERT methods for implementing the foundation construction of the GKT project using the planned and actual schedules has been able to optimize the work, namely 123 days using the planned schedule and 150 days using the actual schedule. These results have found the critical path, so that by applying the CPM and PERT methods in this project, an estimated schedule can be obtained to speed up the project. The cost difference using the CPM, PERT and CPM-PERT methods for the planned schedule is IDR 304,000,000 (Three Hundred and Four Million Rupiah) , Rp. 264,000,000 (Two Hundred and Sixty Four Million Rupiah) and Rp. 264,000,000 (Two Hundred and Sixty Four Million Rupiah). The difference in costs using the CPM, PERT, CPM-PERT method for the actual schedule is IDR 344,000,000 (Three Hundred Forty Four Million Rupiah), IDR 304,000,000 (Three Hundred Forty Four Million Rupiah) and IDR 304,000,000 (Three Hundred Forty Four Million Rupiah). These costs will be the contractor's profit.
A RaniHafnidar. (2016). Manajemen proyek konstruksi.
Abdillah Army Wildan. (2019). Analisa Network Planning Menggunakan Critical Path Method Dalam Manajemen Proyek .
Ahayun Anggara. (2017). Perencanaan Dan Pengendalian Proyek Dengan Metode PERT – CPM: Studi Kasus Fly Over Ahmad Yani, Karawang.
Astuti Tri Devi. (2021). Analisa Pengendalian Manajemen Waktu Proyek Pembangunan Gedung SS Islamic Center dengan Metode Network Planning.
Aulady Ferdaus Noor, Orleans, CesaltinoMohamad. (2016). Perbandingan Durasi Waktu Proyek Konstruksi Antara Metode Critical Path Method (CPM) dengan Metode Critical Chain Project Management (Studi Kasus: Proyek Pembangunan Apartamen Menara Rungkut).
AuliaM Zikril. (2021). Penerapan Metode CPM (critical path method) Pada Proyek Konstruksi Pembangunan Bendungan Lau Simeme Paket II Kab. Deli Serdang.
Catur Ayu Ardania Widyati, Rahmat Muslim Rajab Syafrizal, Imam Machdi Wiwiek. (2022). Statistik Indonesia: Statistical Yearbook of Indonesia 2022. Jakarta.
Ekanugraha Rakhmat Arif. (2016). Evaluasi Pelaksanaan Proyek.
Ezekiel R. M. IwawoTjakra, Pingkan A. K. PratasisJermias. (2016). Penerapan Metode CPM Pada Proyek Konstruksi (Studi Kasus Pembangunan Gedung Baru Kompleks Eben Haezar Manado).
Fadli MTST. (2012). Pengolahan Air Bersih dengan Proses Saringan Pasir Lambat Pengolahan Air Bersih dengan Proses Saringan Pasir Lambat.
Iluk Tsalist. (2020). Penerapan Metode CPM Dan PERT Pada Gedung Parkir 3 Lantai Grand Panglima Polim Kediri.
Iwawo R. M.Ezekiel. (2016). Penerapan Metode CPM Pada Proyek Konstruksi (Studi Kasus Pembangunan Gedung Baru Kompleks Eben Haezar Manado).
Jack R. Meredith J. Mantel, Jr.Samuel. (2006). Project Management: A Managerial Approach.
Melissa Guning2017. (2017). Strategi Pertumbuhan Jemaat (Studi Kasus: Pada Gereja Kharismatik GPI Berkemenangan, di Jl. Tuasan . Medan.
Satyawisudarini Dewi Yusdiana dan Inne Eva. (2018). Penerapan Metode PERT Dan CPM Dalam Pelaksanaan Proyek.
Setiawatisri. (2016). Penerapan Metode CPM Dan PERT Pada Penjadwalan Proyek Konstruksi (Studi Kasus: Rehabilitasi / Perbaikan Dan Peningkatan Infrastruktur Irigasi Daerah Lintas Kabupaten/Kota D.I Pekan Dolok).
SoehartoIman. (1999). Manajemen Proyek : Dari Konseptual Sampai Operasional. Edisi 2, Cetakan 1.
Telaumbanua Aprianus. (2022). Pengembangan E-Module Manajemen Konstruksi pada Program Studi Pendidikan Teknik .
This work is licensed under a Creative Commons Attribution 4.0 International License
Authors who publish with this journal agree to the following terms:
The UMA Open Access Journals provides quality journal publication services to documenting and preserving scientific article from the results of your research.